Pernyataan mengenai projek terbengkalai mengikut pecahan negeri di seluruh Malaysia.

Posted on Monday, 10-11-2008Monday, 10-11-2008 by DAP Seputeh

Tarikh : 5 November 2008

Soalan : 24

YB Puan Teresa Kok Suh Sim (Seputeh) minta Menteri Perumahan Dan Kerajaan Tempatan menyatakan projek terbengkalai mengikut pecahan negeri di seluruh Malaysia. Apakah langkah yang diambil oleh Kementerian untuk menyelamatkan projek perumahan yang terbengkalai dan berapakah projek perumahan terbengkalai telah pun dipulihkan melalui campur tangan pihak Kementerian.

Jawapan:

Tuan Yang Dipertua,

Bagi tempoh 1990 sehingga Jun 2008, terdapat sejumlah 270 projek perumahan terbengkalai di Semenanjung Malaysia. Daripada jumlah tersebut, 126 projek telah disiapkan dengan Sijil Layak Menduduki, 29 projek sedang dalam pembinaan manakala 115 projek masih terbengakalai. Pecahan mengikut negeri adalah seperti berikut:

NEGERI

SIAP DIPUILIHKAN

SEDANG DALAM PEMBINAAN

MASIH TERBENGKALAI

JUMLAH

Perlis

3

0

0

3

Kedah

11

2

7

20

Pulau Pinang

16

2

8

26

Perak

14

1

5

20

Selangor

27

4

35

66

W.Persekutuan, KL

12

3

3

18

N.Sembilan

9

4

16

29

Melaka

7

1

6

14

Johor

5

9

23

37

Pahang

10

2

9

21

Terengganu

7

0

1

8

Kelantan

5

1

2

8

Jumlah

126

29

115

270

Untuk makluman Ahli Yang Berhormat, dalam usaha-usaha pemulihan projek perumahan terbengkalai, Kementerian memainkan peranan sebagai pemudahcara/mediator dengan menyelaraskan mesyuarat, perbincangan dan rundingan bersama semua pihak yang terbabit seperti pemaju, tuan tanah, pembeli, pembiaya atau juruperunding serta agensi-agensi kerajaan seperti Jabatan Insolvensi Malaysia, Pihak Berkuasa Tempatan (PBT) dan Pejabat Tanah bagi mencari kaedah pemulihan yang terbaik. Hasil pemudahcaraan Kementerian ini, sebanyak 126 projek perumahan terbengkalai telah siap dipulihkan dengan Sijil Layak Menduduki.

Kementerian PErumahan dan Kerajaan Tempatan

November 2008

5 thoughts on “Pernyataan mengenai projek terbengkalai mengikut pecahan negeri di seluruh Malaysia.”

  1. lee wee tak says:
    Tuesday, 11-11-2008 at 07: 53.23

    the answer did not mention about the plight of the house buyers and any assistance to them? The errand developers should be hunted down and held accountable.

    How come so many bombed-out projects were approved in the first place? Could the project failure be detected at approval stage? Was there sufficient checks to ensure the projects can be completed? Was there an avenue of assistance for developers to seek when they ran into trouble?

    It is time we encourage Build then Sell concept. For starters, the tax law can be amended to encourage this. Let the Build then Sell developers to be assessed on tax on units sold basis, rather than on percentage of completion basis. Also, exempt them from advance corporate tax (CP 204).

    The developers can pay taxes after a sale is made, rather than setting aside some of the funds for taxes while the project is on-going.

  2. KFTANG says:
    Tuesday, 11-11-2008 at 22: 33.18

    Looks like Selangor has the most number of housing projects with 35 still abandoned. This is alarming considering Selangor is the most ‘developed’ state in the country. Something urgent and immediate should be done to alleviate the financial hardships of those who have booked their units in these abandoned projects. They have to service their housing loans, besides having to pay for their house rentals presently while awaiting for these abandoned houses to be restarted and completed again.

  3. ventura says:
    Wednesday, 12-11-2008 at 23: 48.37

    Look like the statistic tabulation is described as below:-

    15 projects abandon average per year
    42.6% abandoned
    57.4% revived
    10.7% work in progress

    It all began in the issuing of the permit and license to back up the project, bank guarantee and government surety should be consistent with developer and buyer of the property therein. Unfortunately when the developer call the short all it goes is the plight of the house buyer being bombarded with many of the financial toil that suffer as a consequences of such a mistakes or uncompetitive business in sight.

    I believe they should not just mere act as a middleman or mediator to negotiate for the reviving application, but should take up the surety of the completion of the projects.

    It all started from the beginning the criteria have to permit the developer to start the project:
    1) Background of the developer is essential for evaluation and experience versus the risk return to the scale of the projects.
    2)Backup banker that are willing to support the project completion and analyze of the projected economy predicament in future that might have impact and influence to the projects wobbility and versatility envisage.
    3) Government policies and surety to make sure that the developer will able to have the resources and complete the project in the worse case scenarios.
    4) Protection and surety to the buyers that have took up the purchase or insurance coverage on that property bought should the project is abandon.

    I believe that government is enforcing the at time completion report do the enforcement handed in timely or being sent to the site to verify and testify that such a percentages being built as a result?

    What are the term and condition that has tricked the buyer into sales & purchase and later on purportedly denial of such a promise. True example: Sutramas Apartment Puchong were being promise a car park at the stage of marketing and even stated in the brochures but later on the S&P it did not stated but put the car park as separate parcel and end up the residence has to pay extra money in term of servicing the loan and car park. The answer to the changes of the agreement is that the developer has actually miscalculated the cost of the building and as a result this car park is place in that manner.

    Despite many complaint even right to the very ear of Minister of Housing and Development the plight was vain.

    So what would the government take into consideration should this matters as above happening even as to many housing development projects.

    The last Minister of the Housing and Development head was not doing any good job therefore they have actually lost over 400 voters support within this projects issues. Down to cryonism and corruption within the projects!

    Despite many complaints even right to the very ear of Minister of Housing and Development the plight was vain.

    So what would the government take into consideration should this matters as above happening even as to many housing development projects.

    The last Minister of the Housing and Development head was not doing any good job therefore they have actually lost over 400 voters support within this project issues. Down to very ADUN on cronyism and corruption within the projects!

  4. wongyingshiuan says:
    Friday, 21-11-2008 at 15: 58.10

    Hi,

    I have bought the double storey in Lestari puchong in year 2003 and it is already stop work till now almost 5 year ++, but there is not starting work since TALAM have take over by IJM, the government keep on depromises buyer, and the TALAM still can earn money. We want to know the status of house at Lestari Puchong near Sri Kembangan when can be start work !!!!!!!!

    We are facing financial problem already, and we cannot stop payment at bank, so we need hand for helping us.

    PLEASE………………. we really poor already since the economy go down already.

  5. wongyingshiuan says:
    Friday, 28-11-2008 at 14: 19.56

    Puan Teresa Kok,

    Need your great help to check the status of the developer TALAM Corporation Bhd is really IJM will take over the Lestari Puchong project of double storey link house will they resume the work.

    I have bought the double storey in Lestari puchong in year 2003 and it is already stop work till now almost 5 year ++, but there is not starting work since TALAM have take over by IJM, the government keep on depromises buyer, and the TALAM still can earn money. We want to know the status of house at Lestari Puchong near Sri Kembangan when can be start work !!!!!!!!

    We are facing financial problem already, and we cannot stop payment at bank, so we need hand for helping us.

    PLEASE………………. we really poor already since the economy go down already.

    Thnaks

Comments are closed.

About

Teresa Kok

About Teresa

Teresa Kok (郭素沁) is Seputeh's MP and DAP Vice-chairman. Born and bred in Kuala Lumpur, Teresa is a second-generation Malaysian of Chinese descent. n the 2008-2013 term she was Selangor Senior State Executive Councillor for Investment, Industry and Trade and State Assemblyperson for Kinrara.

Learn More

Recent Articles

  • 𝐉𝐊𝐏𝐓𝐆 𝐦𝐞𝐥𝐮𝐥𝐮𝐬𝐤𝐚𝐧 𝐩𝐞𝐧𝐲𝐞𝐰𝐚𝐚𝐧 𝐭𝐚𝐩𝐚𝐤 𝐬𝐞𝐤𝐨𝐥𝐚𝐡 𝐭𝐞𝐫𝐛𝐞𝐧𝐠𝐤𝐚𝐥𝐚𝐢, 𝐒𝐊 𝐃𝐚𝐧𝐚𝐮 𝐏𝐞𝐫𝐝𝐚𝐧𝐚 𝐤𝐞𝐩𝐚𝐝𝐚 𝐬𝐲𝐚𝐫𝐢𝐤𝐚𝐭 𝐩𝐞𝐧𝐣𝐮𝐚𝐥 𝐤𝐞𝐫𝐞𝐭𝐚 𝐭𝐚𝐧𝐩𝐚 𝐝𝐚𝐩𝐚𝐭 𝐩𝐞𝐫𝐬𝐞𝐭𝐮𝐣𝐮𝐚𝐧 𝐊𝐏𝐌
  • 𝐌𝐄𝐍𝐓𝐄𝐑𝐈 𝐏𝐄𝐌𝐁𝐀𝐍𝐆𝐔𝐍𝐀𝐍 𝐖𝐀𝐍𝐈𝐓𝐀, 𝐊𝐄𝐋𝐔𝐀𝐑𝐆𝐀 𝐃𝐀𝐍 𝐌𝐀𝐒𝐘𝐀𝐑𝐀𝐊𝐀𝐓 𝑑𝑖𝑚𝑖𝑛𝑡𝑎 𝑚𝑒𝑛𝑦𝑎𝑡𝑎𝑘𝑎𝑛 𝑎𝑝𝑎𝑘𝑎ℎ 𝑝𝑟𝑜𝑠𝑒𝑑𝑢𝑟 𝑚𝑒𝑛𝑑𝑎𝑓𝑡𝑎𝑟𝑘𝑎𝑛 𝑃𝑢𝑠𝑎𝑡 𝐾ℎ𝑖𝑑𝑚𝑎𝑡 𝐼𝑏𝑢 𝑆𝑒𝑙𝑒𝑝𝑎𝑠 𝐵𝑒𝑟𝑠𝑎𝑙𝑖𝑛 (𝐶𝑜𝑛𝑓𝑖𝑛𝑒𝑚𝑒𝑛𝑡 𝐶𝑒𝑛𝑡𝑟𝑒).
  • 𝐊𝐄𝐍𝐘𝐀𝐓𝐀𝐀𝐍 𝐌𝐄𝐃𝐈𝐀 𝐘𝐁 𝐏𝐄𝐍𝐆𝐄𝐑𝐔𝐒𝐈 𝐏𝐀𝐂 𝐁𝐀𝐆𝐈 𝐏𝐄𝐌𝐁𝐄𝐍𝐓𝐀𝐍𝐆𝐀𝐍 𝐏𝐄𝐍𝐘𝐀𝐓𝐀 𝐏𝐀𝐂 𝐁𝐄𝐑𝐇𝐔𝐁𝐔𝐍𝐆 𝐏𝐄𝐍𝐆𝐔𝐑𝐔𝐒𝐀𝐍 𝐊𝐀𝐖𝐀𝐋𝐀𝐍 𝐇𝐀𝐑𝐆𝐀 𝐃𝐀𝐍 𝐒𝐔𝐁𝐒𝐈𝐃𝐈 𝐌𝐈𝐍𝐘𝐀𝐊 𝐌𝐀𝐒𝐀𝐊 𝐃𝐈 𝐁𝐀𝐖𝐀𝐇 𝐊𝐄𝐌𝐄𝐍𝐓𝐄𝐑𝐈𝐀𝐍 𝐏𝐄𝐑𝐃𝐀𝐆𝐀𝐍𝐆𝐀𝐍 𝐃𝐀𝐋𝐀𝐌 𝐍𝐄𝐆𝐄𝐑𝐈 𝐃𝐀𝐍 𝐊𝐎𝐒 𝐒𝐀𝐑𝐀 𝐇𝐈𝐃𝐔𝐏 𝐏𝐀𝐃𝐀 𝟏𝟔 𝐉𝐔𝐋𝐀𝐈 𝟐𝟎𝟐𝟔
  • (no title)
  • UCAPAN PERBAHASAN RANG UNDANG-UNDANG PROFESION KERJA SOSIAL OLEH TERESA KOK, AHLI PARLIMEN SEPUTEH PADA 14 JULAI 2026
  • MENTERI PERLADANGAN DAN KOMODITI diminta menyatakan status penaiktarafan semua depot biodiesel di Malaysia untuk menyimpan, mengadun dan mengedar biodiesel B20
  • Pembatalan Penyewaan Tapak Bekas SK Danau Perdana Bukti Keperluan Reformasi Tadbir Urus Tanah Persekutuan (14 Julai 2026)
  • 郭素沁:撤销前达瑙柏兰岭国小旧址租约 反映联邦土地治理须改革
  • Govt Urged to Implement PAC Recommendation to Establish KL Land Committee After SK Danau Perdana Lease Reversal (14 July 2026)
  • 𝐌𝐄𝐍𝐓𝐄𝐑𝐈 𝐏𝐄𝐌𝐁𝐀𝐍𝐆𝐔𝐍𝐀𝐍 𝐔𝐒𝐀𝐇𝐀𝐖𝐀𝐍 𝐃𝐀𝐍 𝐊𝐎𝐏𝐄𝐑𝐀𝐒𝐈 𝑑𝑖𝑚𝑖𝑛𝑡𝑎 𝑚𝑒𝑛𝑦𝑎𝑡𝑎𝑘𝑎𝑛 𝑗𝑢𝑚𝑙𝑎ℎ 𝑎𝑑𝑢𝑎𝑛 𝑑𝑖𝑡𝑒𝑟𝑖𝑚𝑎 𝑜𝑙𝑒ℎ 𝐾𝑒𝑚𝑒𝑛𝑡𝑒𝑟𝑖𝑎𝑛 𝑏𝑒𝑟ℎ𝑢𝑏𝑢𝑛𝑔 𝑑𝑎𝑘𝑤𝑎𝑎𝑛 𝑟𝑎𝑠𝑢𝑎ℎ 𝑚𝑒𝑙𝑖𝑏𝑎𝑡𝑘𝑎𝑛 𝑘𝑜𝑝𝑒𝑟𝑎𝑠𝑖 𝑑𝑎𝑙𝑎𝑚 5 𝑡𝑎ℎ𝑢𝑛 𝑦𝑎𝑛𝑔 𝑙𝑒𝑝𝑎𝑠.
  • UCAPAN TERESA KOK DALAM PERBAHASAN RUU PINDAAH AKTA KAWALAN PADI DAN BERAS 1994 PADA 9 JULAI 2026
  • Perbahasan berkenaan Penambahbaikan Perkhidmatan Bersepadu One Stop Crisis Center (OSCC) pada 9 Julai 2026
  • KSN DAN KP JKPTG DISERU MEMBATALKAN KONTRAK PENYEWAAN TAPAK SEKOLAH (LOT 54836) DI TAMAN DESA KEPADA SYARIKAT SWASTA
  • MENTERI PENDIDIKAN diminta menyatakan bilangan murid-murid darjah satu di setiap sekolah rendah jenis kebangsaan Cina di kawasan Parlimen Seputeh dan Bukit Bintang pada tahun 2023, 2024, 2025 dan 2026
  • Ucapan Perbahasan Teresa Kok (Seputeh) Laporan SUHAKAM 2024 Pada 7 Julai 2026

Article Archives

© 2026 TERESAKOK | Powered by Minimalist Blog WordPress Theme